Office building construction cost

How much does it cost to build a commercial building?

How to estimate construction costs for commercial projects Establish the building quality class. Calculate the area of the first floor. Multiply that by square foot costs estimates as explained above. Add the costs of mechanical and electrical fixtures. Add the costs for the second and higher floors.

How much does it cost to build a 5 story office building?

Office, 5-10 Story Square Foot Cost Assuming Face Brick with Concrete Block Back-up / R/Conc. Frame

Cost Estimate (Union Labor) % of Total Cost Per SF
Total $125.63
Contractor Fees (GC,Overhead,Profit) 25% $31.41
Architectural Fees 6% $9.42
Total Building Cost $166.45

What is the construction cost per sq ft?

Most housing projects cost between $150 and $200 per square foot . Again, this depends on the bells and whistles, but that’s a good number to start with . As far as the cost of your land, the numbers can vary wildly depending on where you’re looking to post up.

How much does it cost to build out an office space?

From design, architecture, construction, furniture, fixtures, IT implementation and more—the average cost to build out an office is $196.49 per square foot. This figure varies across the U.S. where construction labor is tight and office development is in high demand.

How do you estimate building costs?

For example, if your new home is to be 2,000 square feet and your builder estimated that it would cost $350,000 to build , then your cost per square foot is 300,000 divided by 2,000, or $175.

You might be interested:  How to get construction loan

Who pays for commercial build out?

The most common way that landlords pay for commercial leasehold improvements is with a Tenant Improvement Allowance (TIA). A TIA is a certain amount of money (a fixed amount or an amount per square foot) that the landlord gives you to make improvements. If the cost of improvements exceeds the TIA, you pay the extra.

How much does a 7 story building cost?

Apartment, 4-7 Story Square Foot Cost Assuming Decorative Concrete Block / R/Conc. Frame

Cost Estimate (Open Shop) % of Total Cost Per SF
Total $115.16
Contractor Fees (GC,Overhead,Profit) 25% $28.79
Architectural Fees 7% $10.08
Total Building Cost $154.02

How much does it cost to build a 20 story apartment building?

Apartment Building Cost by Number of Units

Number of Units Average Cost Range
12 $3.1-$16.5 million
20 $3.1-$ 20 million
24 $3.1-$25 million
50 $7-$50 million

How much does it cost to build a 2000 sq ft building?

Average Cost to Build a House by Square Footage

Square Footage Average Cost to Build
2,000 sq.ft. $326,000
3,000 sq.ft. $489,000
3,500 sq.ft. $570,500
4,000 sq.ft. $652,000

How do you calculate price per square foot?

Price per square foot is calculated by dividing the price of the home by the square footage of the home to come up with a price per square foot number. For example, if the price of the home is $100,000 and it is 1,000 square feet , the price per square foot is $100.

How many sq ft is 30×40?

Square footage is calculated by multiplying width by length. So if a area is 30 foot wide by 40 foot long, 30 x 40 = 1200 square feet.

You might be interested:  Construction performance bond cost

What is the cost of residential construction?

New home construction costs $100 to $155 per square foot on average with most homeowners paying $155,000 to $416,250 , in addition to the cost of your land. Costs vary considerably based on location and all your choices in design and interior and exterior finishes.

How much is a 10000 square foot building?

Example Square Foot Building Costs:

Building Size (ft) Square Footage (SF) Estimate Cost
80×100 8,000 $59,800
100×100 10,000 $74,800
100×200 20,000 $142,000
150×250 37,500 $266,250

How much does it cost to build a small office building?

What is the budget? According to 42Floors (a search engine for professional real estate ) – the average cost of a basic build -out in a new building can begin around $40 per square foot (which includes carpeting, paint, lighting and equipment such as a photocopier and coffee machine).

How long does an office build out take?

Depending on what you are specifically wanting to configure, you can expect a shell space build – out to take up to eight months. Shell Condition Build – Out Schedule.

Timeline for Build Out of Shell Space
Design/Architecture 10 Weeks
Bidding & Permitting 6 Weeks
Construction 16 Weeks
Total 32 Weeks (8 Months)