Construction bulletin vs addendum

What is an addendum in construction?

Addendum (Addenda) Written information adding to, clarifying or modifying the bidding documents. An addendum is generally issued by the owner to the contractor during the bidding process and as such, addenda are intended to become part of the contract documents when the construction contract is executed.

What is a construction bulletin?

A Bulletin is used to issue changes AFTER bid proposals are submitted by the bidding contractors, and probably AFTER the contract is signed between the owner and the successful bidder. Revisions issued via a Bulletin may have cost impact. They may qualify for changes orders.

How do you number an addendum?

Addenda should only be used to change the “terms” an an Agreement. Addenda must be sequential [ #1, #2, #3, etc.] Addenda must be sequential [ #1, #2, #3, etc.] An Addendum to a document other than the Purchase Agreement may be labeled as an Addendum for that particular document [ Addendum #TDS, Addendum #SPQ, etc.]

What do construction documents include?

During construction documentation the architect will prepare drawings, specifications and schedules that define the detailed requirements for the construction of the building and will be used in the construction process. Note that timeframes for building approval will vary.

What is an addendum example?

An addendum can consist of everything from lease terms, to the correction of a mistake that was not noticed until after the document was signed. For example , an addendum to a separation agreement often covers visitation schedules for holidays that were not previously listed in the initial visitation schedule.

You might be interested:  Garage construction cost estimates

What does addendum mean?

An addendum is an attachment to a contract that modifies the terms and conditions of the original contract. Addendums are used to efficiently update the terms or conditions of many types of contracts.

What is a bulletin?

(Entry 1 of 2) 1 : a brief public notice issuing usually from an authoritative source specifically : a brief news item intended for immediate publication or broadcast. 2 : periodical especially : the organ of an institution or association. bulletin .

What’s a variation order?

A variation (sometimes referred to as a variation instruction, variation order (VO) or change order ), is an alteration to the scope of works in a construction contract in the form of an addition, substitution or omission from the original scope of works.

What is a change directive in construction?

• A Change Directive (CD) is a written instruction prepared by the Consultant and signed by the Owner directing the Construction Manager to proceed with a change . in the Work within the general scope of this Contract prior to the Owner and the Construction Manager agreeing upon an adjustment, to avoid progress delays.

How do you start an addendum?

Writing a Contract Addendum When writing your addendum , follow these guidelines: Use the same font, margins, and style used in the original contract. Reference the original contract by name and date, with a title that makes it clear that this new document is an addendum . Name the parties to the contract.

What does an addendum look like?

The addendum needs to look like the original contract so that it is clear the two documents are connected. Reference the date of the original contract. Title the document in a way that shows it is an addendum to the original contract. For example: ” Addendum to January 2, 2009 Employment Contract”.

You might be interested:  How do you abbreviate construction

How do you use an addendum?

Using Addendum in a Sentence When to use Addendum : Addendum is a singular noun that refers to something, especially additional text or documents, added to something else. Usually this added content is included at the end of a document. It can also refer to the appendix of a book.

What is the purpose of construction documents?

The construction documents define the quantities and qualities of, and relationships among, all materials required to construct a project; they establish the contractual obligations for the University and the contractor, and they define the roles of the construction team members (see 1.4).

What are the two key items that make up construction documents?

The two major components that make up the contract documents are the drawings and the project manual.

What order do construction drawings go in?

Drawings are always organized from most general to most specific or specialized. Since plans are most helpful to see the overall design of the project, they come first. Elevations and sections are a bit more specific and come next followed by details and schedules, which are the most specific type of drawings .